Alexandria Park Community School
Client: DECC/Richard CrookesLocation: Belmont Street, Alexandria Our involvement: Potential settlement and CBR assessment Footing and building pad inspections Scaffoldingf certification Batter stability advice Temporary shoring and adaptive geotechnical...
Cambridge Hotel Early Works
Client: DECCLocation: Riley Street, Surry Hills Our involvement: Existing capping beam bearing pressure assessment Piling rig foundation certification. Project Challenges: The Cambridge Hotel early works involved the demolition and rebuild of an existing...
Surfside Data Centre
Client: Canberra Data Centres/Hindmarsh ConstructionLocation: Roberts Road, Eastern Creek Our involvement: Geotechnical investigations Soil Sampling Point Load Rock Strength Testing Mobile Crane foundation certification Controlled fill Certification Footing...
Long Street Quarry – Goulburn
The disused Long Street Quarry was a set for the feature film “Hacksaw Ridge”, where actors/stunt men had to climb up and down faces of the quarry. The section of cliff face that was used for filming was located at the northern end of the quarry, and comprised a ~20m...
East Bowral Reservoir
Project Type: Slope Stability AssessmentClient: Wingecarribee Shire CouncilDuration/Year: 6 months/2012 The reservoir was constructed in 2006, and is a ~30m diameter, circular concrete structure, located within an infilled drainage depression on the slope of a hill....
7 Wilson Street, Scarborough, NSW
Project Type: Slope Stability AssessmentsClient: Bruce MarshallDuration/Year: 3 months/2016 Localised remediation on a portion of a slope which had experienced a large scale landslide (>500m long). This included slope stability analysis, material assessment, and...
Thredbo & Perisher Ski Lodges
Project Type: Slope Stability AssessmentsClient: VariousDuration/Year: 6 months/2000 to 2010 ACT Geotech carried out geotechnical slope instability assessments for 30+ lodges in Thredbo & Perisher following the Thredbo landslide. Lodges included Thredbo, Smowman,...
28 Kalang Cres, Jerrabomberra, NSW
Project Type: Slope Stability AssessmentsClient: VariousDuration/Year: 3 months each/2015 & 2016 Slope instability risk assessments for residential developments is areas of known or historical slope instability. This included slope stability analysis, material...
Kingswood Residential Development
Project Type: Apartment Development The Kingswood residential development is located at 28 to 32 Rodgers Street, in Kingswood, NSW. The project involved the construction of 7 storey residential towers and 2 basement parking levels which will extend to ~5-6m depth...